Happy Holidays everyone! I hope the last few weeks have been very enjoyable and relaxing. It is always nice to end the chaotic year with a few weeks of holiday activities surrounded by family and friends!
Before the holiday break, we were hard at work on the course completing the bunker renovation project on 18 North. All three bunkers came out really great and we are extremely satisfied with the efforts of the staff in less than desirable working conditions. We managed to put drainage in, spray liner, and fully sand all three bunkers. The video below shows me spraying the liner in:
The sand is at a USGA spec depth of 4-5 inches. We used a 2mm double screened sub-angular bunker sand. Once we sanded the bunkers, we used a plate compactor to pack the sand so the sand would be able to receive incoming shots. Here are some finished pictures.
I understand your next question…When are you going to do the rest? We will be working diligently this Spring to complete as many as we can. Unfortunately, it is very time consuming and labor intensive. It took us 2 weeks to finish the three bunkers on 18. The next ones we will be working on include 8 North, 2 North, and 12 North.
Now that the holidays are over, we are doing as much on course cleanup as possible. We still have debris from the October snow storm. We also have selected trees on the course to clean up that we took down this past Fall. Course maintenance has been limited to cleanup and selected cup rotation this time of year. Thank you for your continued support! With no snow in the forecast, I’m sure we will see you on the course!
-Jason VanBuskirk, Superintendent
February 22, 2012 at 4:15 PM
Great look at the finished product. How often do you replace the bunkers in MA. Our primary service location is drastically different from the northeast as we’re in Atlanta. Regardless, great work!